EXPANDING THU DUC WATER PLANT - PHASE V

1.      Requirement and current conditions

1.1. Requirement and current conditions

-                Requirement: based on Draft general plan of HCMC water supply until 2025 designed by VIWASE in May 2008 (the final report)

-                Current conditions:

+ It is possible to build the plant in the area of residential houses of staffs of Thu Duc Water Plant

+ Clean water pump station and raw water pump station built in phase 3

+ to build a new clean water pump station with capacity of 500,000 m3/day

+ to build clean water tank with capacity of 300,000 m3/day

+ Having trouble in clearing security corridor of raw water and clean water pipe systems built from 1965 to serve for development projects

+ Difficult in clearing land to build D.2400 raw water transfer system from Hoa An to Thu Duc.

1.2. Masterplan:

-                Draft general plan of HCMC water supply until 2025 designed by VIWASE in May 2008 (the final report)           

1.3. Objective: to supplement water system for HCMC

1.4. Capacity, location, total area, construction items, land

-                Estimated capacity: 500,000m³/day

-                Location: Thu Duc district, HCMC.

-                Total area : 2.5 ha

1.5. Technology & conditions

+ Technological system as same that of Thu Duc 3 Water Plant (lamenlla across deposit)

+ Construction in the area of Thu Duc Water Plant (clearing space of residential houses of Thu Duc Water Plant,…)

1.6. Total investment capital, form of investment, time of investment

-                Total investment capital: VND2,500 billion

-                Form of investment: J.V

-                Time of investment: 2020 – 2024.

2.      Procedures and contact

-                Procedures of the project investment: doing Investment project Report for approval (Group A project)

-                Contact:         Saigon Water Corporation