Project developer: Department of Transport Address: 63 Ly Tu Trong Street, District 1, HCMC, Vietnam Tel: (84-8) 829451 - 8292204, Fax: (84-8) 8290458 E-mail: sgtvt@tphcm.gov.vn Website: www.sgtvt.hochiminhcity.gov.vn Objective - The route of Binh Tien prolonged (including canal crossing bridges over Tau Hu Canal and Doi Canal) has been clearly planned in the masterplan of District 8 and Binh Chanh District.
- It combines to municipal remodeling and improves centripetal routes, including National Highway 50 and complete construction of transportation corridors to the South of the City.
Location: Binh Chanh District, district 6 and district 8 Scale - Length: 3.25km; Cross section area: 30m
- Routing: from Binh Tien – Pham Van Chi crossroad in district 6 to Binh Chanh District then connected to traffic intersection of by-pass route National Highway 50 and Nguyen Van Linh
- Road section:
- In District 6: 286.4m
- Section between 2 bridges over canal: 254.8m
- Section connected to Nguyen Van Linh: 2,134.7m
- Reinforced concrete bridge and reinforced prestressed concrete bridge, standard: 100 years
- Calculated live load: HL 93
- Walking group loading: 3x10-3 Mpa
- Navigational clearance: BxH = 40mx6m
- Length: bridge over Tau Hu Canal: 173.35m, bridge over Doi Canal: 356.6m
- Cross section area: 31m (4 car traffic lanes, 2 mixed traffic lanes)
Investment capital: estimated at VND 11,200 billion (~US$ 700 million) Form of investment: BOT and urban rehabilitation Priority level: 1 |